Kellyton Graphite Plant
July 2025 – PHASE 1 – INSTALLATION & TESTING OF MILLING AND SHAPING EQUIPMENT CONTINUES
WESTWATER KELLYTON: MILLING AND SHAPING PROGRESS


All Closed
display: none;
FEBRUARY 2025 – PHASE 1 – COMPLETION OF STRUCTURAL STEEL, AND DUST COLLECTORS – INSTALLATION OF PIPING AND CONTROLS UNDERWAY
FEBRUARY 2025 – PHASE 1 – COMPLETION OF STRUCTURAL STEEL, AND DUST COLLECTORS – INSTALLATION OF PIPING AND CONTROLS UNDERWAY
WESTWATER KELLYTON: MILLING AND SHAPING PROGRESS

JULY 2024 – PHASE 1 – INSTALLATION PROGRESS OF STRUCTURAL STEEL, MILLING, AND DUST COLLECTION
WESTWATER KELLYTON: MILLING AND SHAPING PROGRESS

JUNE 2024 – PHASE 1 – INSTALLATION PROGRESS OF STRUCTURAL STEEL, MILLING, AND DUST COLLECTION
WESTWATER KELLYTON: MILLING AND SHAPING PROGRESS



MAY 2024 – PHASE 1 – INSTALLATION PROGRESS OF STRUCTURAL STEEL, MILLING, AND DUST COLLECTION
WESTWATER KELLYTON: MILLING AND SHAPING PROGRESS



APRIL 2024 – PHASE 1 PROGRESS CONTINUES WITH THE INSTALLATION OF STRUCTURAL STEEL AND MILLING DUST COLLECTION
WESTWATER KELLYTON: MILLING AND SHAPING PROGRESS



MARCH 2024 – PHASE 1 PROGRESS CONTINUES WITH THE INSTALLATION OF STRUCTURAL STEEL AND MILLING DUST COLLECTION
WESTWATER KELLYTON: MILLING AND SHAPING PROGRESS



NOVEMBER 2023 – PHASE 1 PROGRESS CONTINUES WITH THE INSTALLATION OF THE MILLING AND SHAPING EQUIPMENT ALONG WITH A NEW R&D LAB




MAY 2023 – PHASE 1 FACILITY STRUCTURES ARE COMPLETE IN PREPARATION FOR EQUIPMENT INSTALLATION.
Westwater teammates continue to receive and stage equipment for installation.








SPG Equipment Delivery Kellyton Advanced Graphite Processing Plant
Continued progress is taking place. Our Team is currently working on roofing and insulation.



January 2023 – CONTINUED PROGRESS IS TAKING PLACE. OUR TEAM IS CURRENTLY WORKING ON ROOFING AND INSULATION. FOUNDATIONS AND EARTHWORKS ARE COMPLETE



Vertical construction of one of the five buildings began in October 2022, assembly of other buildings is underway.


START FOUNDATIONS AUGUST 2022

FOUNDATIONS BEING POURED AND UNDERGROUND UTILITIES BEING INSTALLED – SEPTEMBER 2022

START OF EARTHWORKS MARCH 2022

END OF EARTHWORKS JULY 2022

PRE-CONSTRUCTION MARCH 2022

Contact
Westwater Resources, Inc. (WWR), is an explorer and developer of US-based mineral resources essential to clean energy production.
Sign up to receive emails of all the latest News Releases from Westwater Resources here.
Headquarters
6950 South Potomac Street, Suite 300
Centennial, CO 80112
Kellyton Graphite Processing Plant
349 McClellan Industrial Drive
Kellyton, AL 35089